Last updated:

The Economics of US Power Generation

What each kind of power plant costs to build, to run, and to pay off

Every argument about electricity eventually becomes an argument about money. This page works through the financials of each generating technology on this site: what a plant costs up front, what it costs per watt, how long the money takes to come back, what the staff and maintenance bill looks like, and what a megawatt-hour ends up costing once all of it is added together. The capital and operating figures come from the engineering study Sargent & Lundy prepared for the U.S. Energy Information Administration to support the Annual Energy Outlook 2025. The capacity factors come from this site’s own plant datasets measured against EIA generation data. Every calculation on this page is shown rather than asserted, so you can change an assumption and see where the answer moves.

1. What a power plant costs to build

Overnight capital cost, reference plant, 2023 dollars

The starting number is overnight capital cost: what a developer would pay to build the plant if it could be built instantly, with no interest accruing during construction. It is quoted in dollars per kilowatt of net capacity, which makes plants of very different sizes comparable. Divide by 1,000 and you get the more intuitive cost per watt.

The spread is enormous. A gas combined-cycle plant costs about 87 cents per watt. A two-unit AP1000 nuclear station costs $7.86 per watt, nine times more for the same nameplate capacity. That single ratio explains most of what has been built in the United States over the past two decades.

TechnologyReference
size (MW)
Capital
($/kW)
Cost per
watt
Total project
cost
Fixed O&M
($/kW-yr)
Variable O&M
($/MWh)
Heat rate
(Btu/kWh)
Lead time
(months)
Book life
(years)
Gas combined cycle (2x2x1)1,227$868$0.87$1.065B$12.12$3.416,2664230
Gas peaker (H-class turbine)419$836$0.84$0.350B$6.87$1.249,1423030
Gas peaker (aeroderivative)211$1,606$1.61$0.339B$9.56$5.709,4473030
Gas combined cycle with CCS543$2,365$2.37$1.284B$24.78$5.057,2394230
Coal (ultra-supercritical)650$4,103$4.10$2.667B$61.60$6.408,6386040
Coal with 95% carbon capture650$7,346$7.35$4.775B$86.70$13.7312,2936040
Nuclear (AP1000, 2 units)2,156$7,861$7.86$16.948B$156.20$2.5210,6088460
Nuclear SMR (6 x 80 MW)480$8,936$8.94$4.289B$121.99$3.1910,0467260
Onshore wind200$1,489$1.49$0.298B$33.06$0.0003630
Offshore wind900$3,689$3.69$3.320B$154.00$0.0006030
Solar PV (single-axis track)150$1,502$1.50$0.225B$20.23$0.0002430
Solar PV + 4h battery150$2,175$2.17$0.326B$38.39$0.0002430
Geothermal (binary)50$3,963$3.96$0.198B$150.60$0.0004830
Hydroelectric (new build)100$7,073$7.07$0.707B$33.54$0.0006060
Biomass with 95% CCS50$12,631$12.63$0.632B$261.18$9.6519,9654840
Battery storage (150MW/600MWh)150$1,744$1.74$0.262B$40.00$0.0001820

Overnight capital excludes financing costs and regional multipliers. Lead time is the total from start of development to commercial operation. Heat rate of zero means the technology burns no fuel. The biomass case is the only biomass configuration EIA costed for AEO2025 and it includes 95% carbon capture, which is why it is far more expensive than the roughly $4,500 per kilowatt an uncontrolled biomass plant carried in earlier editions. Battery storage capital is also quoted as $436 per kilowatt-hour of storage.

Reading the total project cost column. These are real amounts of money. The reference nuclear station is a $16.9 billion commitment before a single kilowatt-hour is sold. The reference gas plant is $1.07 billion for slightly more than half the capacity. A 150 MW solar farm is $225 million. The financing, permitting and political problems each of these projects faces are largely a function of which of those numbers is involved.

2. The arithmetic that turns a plant into a price

Levelized cost of electricity, worked line by line

Capital cost alone cannot rank technologies, because a plant that runs constantly spreads its cost over far more electricity than one that runs occasionally. The standard way to compare is the levelized cost of electricity, or LCOE: total lifetime cost divided by total lifetime output, expressed per megawatt-hour. It is the break-even price. Sell above it and the project earns its cost of capital; sell below it and it does not.

Step 1: annualise the capital

A plant is paid for once and earns revenue for decades, so the capital cost has to be converted into an equivalent annual payment, exactly like a mortgage. That conversion is the capital recovery factor:

CRF = i(1 + i)^n / ((1 + i)^n - 1) where i = cost of capital = 7.0% n = cost recovery period = 30 years CRF = 0.07(1.07)^30 / ((1.07)^30 - 1) = 0.08059

So each year the project must produce 8.059% of its capital cost just to service and retire the investment.

Step 2: work an actual plant

Take the reference gas combined-cycle plant: 1,227 MW at $868 per kilowatt, running at the 36.0% capacity factor the US gas fleet actually achieved in 2025.

Total capital: 1,227,000 kW × $868/kW$1,065,036,000
Annual output: 1,227 MW × 8,760 h × 0.3603,869,467 MWh
Annualised capital: $1,065,036,000 × 0.08059$85,832,000/yr
  per MWh: $85,832,000 ÷ 3,869,467$22.18
Fixed O&M: 1,227,000 kW × $12.12/kW-yr = $14,871,000/yr ÷ 3,869,467$3.84
Variable O&M: given directly$3.41
Fuel: 6,266 Btu/kWh = 6.266 MMBtu/MWh × $4.00/MMBtu$25.06
Levelized cost of electricity$54.50/MWh

That is 5.45 cents per kilowatt-hour, and the single largest line is not the plant. It is the gas.

A units trap worth knowing. Heat rate is published in Btu per kilowatt-hour while fuel is priced in dollars per million Btu. The conversion is MMBtu/MWh = heat rate ÷ 1,000, because a megawatt-hour is a thousand kilowatt-hours and a million Btu is a thousand thousand. Getting this wrong by a factor of a thousand makes gas look almost free, which is a mistake worth checking for in any analysis that reports suspiciously cheap thermal generation.

3. The full comparison

Levelized cost by component, sorted cheapest to dearest

Running that same arithmetic across every technology gives the table below. Each row uses the capacity factor the US fleet actually achieved in 2025 where this site has the data, and a stated assumption where it does not.

TechnologyCapacity
factor
CapitalFixed O&MVariable O&MFuelTotal LCOECapital as
% of total
Battery storage (150MW/600MWh)50.0%$37.58$9.13$0.00$0.00$46.7280%
Solar PV + 4h battery50.0%$40.02$8.76$0.00$0.00$48.7882%
Gas combined cycle (2x2x1)36.0%$22.18$3.84$3.41$25.06$54.5041%
Onshore wind32.0%$42.81$11.79$0.00$0.00$54.6078%
Gas peaker (aeroderivative)50.0%$29.55$2.18$5.70$37.79$75.2239%
Solar PV (single-axis track)20.4%$67.73$11.32$0.00$0.00$79.0586%
Gas combined cycle with CCS50.0%$43.51$5.66$5.05$28.96$83.1852%
Geothermal (binary)51.6%$70.65$33.32$0.00$0.00$103.9768%
Nuclear (AP1000, 2 units)92.5%$78.18$19.28$2.52$9.02$108.9972%
Offshore wind45.0%$75.41$39.07$0.00$0.00$114.4866%
Gas peaker (H-class turbine)10.0%$76.91$7.84$1.24$36.57$122.5663%
Coal (ultra-supercritical)46.1%$81.88$15.25$6.40$21.16$124.6966%
Coal with 95% carbon capture50.0%$135.16$19.79$13.73$30.12$198.8068%
Nuclear SMR (6 x 80 MW)50.0%$164.41$27.85$3.19$8.54$203.9981%
Hydroelectric (new build)27.8%$234.05$13.77$0.00$0.00$247.8394%
Biomass with 95% CCS43.6%$266.51$68.38$9.65$49.91$394.4568%

Technologies without a measured 2025 fleet capacity factor on this site are modelled at 50%, except the H-class peaker at 10% and offshore wind at 45%. All figures exclude federal tax credits, which is a significant omission discussed in section 9.

The pattern in the last column. For wind, solar, hydro and nuclear, capital is 70% to 94% of lifetime cost. For gas, capital is around 40% and fuel is more than half. That difference is why gas plants are exposed to commodity markets and renewables are exposed to interest rates, and why the two technologies fail in completely different economic weather.

4. The cost of capital decides more than the technology

Same plants, four different interest-rate environments

Because most of these technologies are mortgages with turbines attached, the interest rate is not a detail. It is frequently the largest single determinant of whether a project is viable. Holding everything else constant and moving only the cost of capital produces this:

Technology4%7%10%13%Increase,
4% to 13%
Nuclear (AP1000, 2 units)$86.92$108.99$133.72$160.24+84%
Hydroelectric (new build)$181.73$247.83$321.87$401.25+121%
Offshore wind$93.18$114.48$138.34$163.91+76%
Coal (ultra-supercritical)$101.57$124.69$150.59$178.36+76%
Solar PV (single-axis track)$59.93$79.05$100.48$123.45+106%
Onshore wind$42.51$54.60$68.14$82.66+94%
Geothermal (binary)$84.02$103.97$126.32$150.28+79%
Gas combined cycle (2x2x1)$48.23$54.50$61.51$69.04+43%

Going from a 4% to a 13% cost of capital raises the cost of nuclear power by 84% and the cost of hydroelectricity by 89%, but raises gas combined-cycle power by only 43%. A capital-heavy, fuel-free plant is essentially a bond; a gas plant is essentially a fuel-conversion service with a modest amount of equipment attached.

The practical consequence. A nuclear plant financed by a regulated utility with a guaranteed rate of return is a fundamentally different asset from the same plant financed on merchant terms. Nothing about the concrete changes. The economics change completely. This is the main reason nuclear construction in the United States has clustered in regulated markets, and the main reason interest-rate rises hit renewable developers harder than gas developers.

5. Capacity factor is the other multiplier

The same capital spread over more or less electricity

Capital cost per kilowatt tells you what a plant costs. Capacity factor tells you how much electricity that purchase actually yields. The two together determine cost per unit far more than either alone.

Capacity factorGas combined cycleNuclearSolar PVOnshore wind
10%$122.16$913.01$161.27$174.72
20%$75.32$462.27$80.63$87.36
30%$59.70$312.03$53.76$58.24
40%$51.90$236.90$40.32$43.68
50%$47.21$191.83$32.25$34.94
60%$44.09$161.78$26.88$29.12
70%$41.86$140.32$23.04$24.96
80%$40.18$124.22$20.16$21.84
90%$38.88$111.70$17.92$19.41

Read the top row. At a 10% capacity factor, nuclear power would cost $913 per megawatt-hour and gas would cost $122. Read the bottom row: at 90%, nuclear is $111.70 and gas is $38.88. The technology did not change. Only the utilisation did.

This is why plant types specialise. A gas peaker uses the cheapest capital available, $836 per kilowatt, because it is expected to run only a few hundred hours a year and cannot spread a large investment over that. A nuclear plant does the opposite: it accepts a very large capital cost because it expects to run more than 90% of every hour of its life. Choosing the wrong technology for a duty cycle is more expensive than choosing the wrong technology.

6. Fuel exposure

What a gas price move does to a combined-cycle plant

Fuel is 52% of the lifetime cost of a gas combined-cycle plant at $4.00 per million Btu, so the gas price passes almost directly into the cost of the electricity.

Gas price
($/MMBtu)
Fuel cost
($/MWh)
Combined-cycle
LCOE
Change from
$4.00 case
$2.00$12.53$41.97$-12.53
$3.00$18.80$48.23$-6.27
$4.00$25.06$54.50base
$5.00$31.33$60.76+$6.27
$6.00$37.60$67.03+$12.53
$8.00$50.13$79.56+$25.06
$10.00$62.66$92.09+$37.60

A plant financed and built at a fixed cost still sees its output cost swing from $41.97 to $92.09 per megawatt-hour purely on fuel, a range of 119%. For comparison, nuclear fuel is $9.02 per megawatt-hour and coal is $21.16, while wind, solar, hydro and geothermal are zero. A doubling of the uranium price moves nuclear power by about 8%; a doubling of the gas price moves gas power by about 46%.

7. How long the money takes to come back

Power price required to repay capital within a given period

Developers and lenders do not usually think in levelized costs. They think about whether the debt gets repaid, and how quickly. The table below inverts the question: given the plant, what flat power price is needed to return the capital, with interest at 7%, within 10, 15, 20 or 30 years?

Technology10-year
payback
15-year
payback
20-year
payback
30-year
payback
Gas combined cycle (2x2x1)$71.51$62.54$58.30$54.50
Onshore wind$87.42$70.11$61.93$54.60
Solar PV (single-axis track)$130.99$103.60$90.66$79.05
Geothermal (binary)$158.15$129.58$116.08$103.97
Nuclear (AP1000, 2 units)$168.94$137.33$122.39$108.99
Offshore wind$172.31$141.81$127.40$114.48
Coal (ultra-supercritical)$187.47$154.37$138.72$124.69
Hydroelectric (new build)$427.29$332.66$287.93$247.83

The 30-year column is the LCOE from section 3, which is the point: levelized cost is simply the break-even price over the full recovery period. The value of the table is the left-hand columns. A gas plant needs $71.51 per megawatt-hour to pay back in a decade, which is well within the range wholesale markets reach. A nuclear station needs $168.94, which is roughly double typical US wholesale power prices, and is the arithmetic reason new nuclear generally requires a regulated rate base, a long-term power purchase agreement, or direct government support to reach a final investment decision.

Payback is not profit. These figures return the capital and its financing cost and nothing more. A developer needs a margin above them, and a plant that merely breaks even over 30 years has produced no return for its equity beyond the assumed 7%. Note also that a nuclear plant with a 60-year book life continues generating for three decades after the 30-year recovery period ends, which conventional LCOE comparisons at a 30-year horizon do not credit.

8. Staff, maintenance and the annual operating bill

What it costs to keep a plant running once it is built

Fixed operations and maintenance is everything the plant spends whether or not it generates: salaries, scheduled maintenance, contracted services, and general administration. It is the number that decides whether an older plant stays open. EIA publishes it as dollars per kilowatt of capacity per year.

For the reference coal plant, the engineering study breaks the bill out in full:

Routine labour$19,403,000/yr
Materials and contract services$15,788,000/yr
Administrative and general$4,851,000/yr
Total fixed O&M, 650 MW plant$40,042,000/yr
Per kilowatt: $40,042,000 ÷ 650,000 kW$61.60/kW-yr

Labour alone is 48% of the fixed bill for a coal plant. Scaling that across the fleet explains a great deal about which technologies survive:

Why this decides retirements. A fully depreciated plant has no capital cost left to recover, so it survives on whether wholesale prices cover fixed O&M plus fuel. For a nuclear plant that floor is roughly $156 per kilowatt-year plus $9 per megawatt-hour of fuel. For a gas plant it is roughly $12 plus the gas price. When power prices fell in the 2010s, that gap is what closed nuclear plants that were technically capable of running for decades more.

9. Strengths and weaknesses, source by source

The financial case for and against each technology

Nuclear

$7.86/W · LCOE $108.99 · 92.5% CF · 84 months to build

  • Highest capacity factor of any source, so capital is spread over more output than anything else
  • Fuel is 8% of cost, so uranium price moves barely register
  • 60 to 80 year life, decades of which are effectively capital-free once paid off
  • $16.9 billion for the reference station, a bet few balance sheets can carry
  • Seven years to build, so the money is committed long before any revenue
  • Most interest-rate-sensitive technology on the list, at +84% from 4% to 13%
  • Needs roughly $169/MWh for a ten-year payback, about double typical wholesale prices

Natural gas

$0.87/W · LCOE $54.50 · 36.0% CF · 42 months to build

  • Cheapest capital per watt of any dispatchable source, by a wide margin
  • Lowest fixed O&M at $12.12/kW-yr, around 30 staff for 1,000 MW
  • Fast to build and least exposed to interest rates of the major technologies
  • Dispatchable, so it earns scarcity prices that flat-output plants cannot
  • Fuel is 52% of lifetime cost, leaving the owner fully exposed to gas markets
  • LCOE swings from $41.97 to $92.09 across a plausible gas price range
  • Carbon capture roughly triples capital, from $868 to $2,365 per kilowatt

Solar PV

$1.50/W · LCOE $79.05 · 20.4% CF · 24 months to build

  • Fastest to build at about two years, so capital is committed for the shortest period
  • No fuel and very low O&M at $20.23/kW-yr
  • Modular, so a project can be sized to the balance sheet rather than the other way round
  • 20.4% capacity factor means capital is spread thinly; it is 86% of lifetime cost
  • Output is fixed to daylight and cannot follow price
  • Adding four hours of storage raises capital 45%, from $1,502 to $2,175 per kilowatt

Wind

$1.49/W onshore · LCOE $54.60 · 32.0% CF · 36 months

  • Lowest levelized cost of any fuel-free source in this analysis
  • Higher capacity factor than solar at similar capital cost per watt
  • Peak output overnight, complementing solar rather than competing with it
  • Offshore costs 2.5 times onshore per watt and 4.7 times as much to maintain
  • Mechanical wear means O&M is 63% higher than solar per kilowatt-year
  • Best sites are remote, so transmission cost is often the real constraint

Coal

$4.10/W · LCOE $124.69 · 46.1% CF · 60 months

  • Fuel is cheap and price-stable at about $2.45/MMBtu
  • Dispatchable and long-lived, with 40-year book life
  • Costs 4.7 times more per watt than gas while producing the same product
  • Fixed O&M is five times gas at $61.60/kW-yr, with roughly 150 staff
  • Adding carbon capture takes capital to $7,346/kW and LCOE to $198.80
  • No new uncontrolled coal plant is economic against gas at any plausible fuel price

Geothermal

$3.96/W · LCOE $103.97 · 51.6% CF · 48 months

  • Baseload output with no fuel cost, a combination only nuclear and hydro share
  • Highest capacity factor among renewables on this site
  • Small unit size, so projects are financeable without utility-scale balance sheets
  • $150.60/kW-yr O&M, the highest of any renewable, because reservoirs need active management
  • Resource risk is unique: drilling can fail after significant capital is spent
  • Geographically constrained to the West without enhanced geothermal techniques

Hydroelectric

$7.07/W new build · LCOE $247.83 · 27.8% CF · 60 months

  • Existing dams are the cheapest electricity in the country, long since paid off
  • 100-year asset lives, far beyond any other technology here
  • Dispatchable and storable, which no other renewable offers at scale
  • New greenfield build is the most expensive option in this analysis at $247.83/MWh
  • 94% of lifetime cost is capital, making it the most rate-sensitive asset on the list
  • The good sites were developed decades ago

Battery storage

$1.74/W, $436/kWh · 18 months to build

  • Fastest asset to deploy, at around 18 months
  • Earns from arbitrage and ancillary services rather than energy volume alone
  • Cell costs have fallen faster than any other technology in this analysis
  • Consumes more electricity than it returns, so it is not a generator and cannot be compared on LCOE
  • Shortest book life here at around 20 years, with capacity degradation throughout
  • Revenue depends on price spreads that additional storage itself erodes

10. What this analysis leaves out

Every levelized comparison hides things, and the honest way to present one is to say which.

On precision. The capital and O&M inputs are engineering estimates for generic plants at non-specific US locations, in 2023 dollars, and real projects vary widely by site, labour market and scope. The capacity factors are measured 2025 fleet averages, which for new plants may understate what modern equipment achieves, particularly for solar. Treat the ordering as robust and the individual figures as indicative.

11. Cross-checking against the market

An analysis that only agrees with itself is not worth much. Lazard publishes an independent levelized cost study built from market data rather than engineering estimates. Its June 2025 edition gives unsubsidised ranges of $50 to $110 per megawatt-hour for gas combined cycle, $37 to $86 for onshore wind, $38 to $78 for utility solar, $66 to $109 for geothermal, $70 to $170 for coal, $70 to $157 for offshore wind, and $140 to $220 for nuclear.

The model on this page lands inside those ranges for gas ($54.50), wind ($54.60), geothermal ($103.97), coal ($124.69) and offshore wind ($114.48). It sits slightly above Lazard for solar, because this page uses the 20.4% capacity factor the existing US fleet actually delivered rather than the higher figure a new tracking plant in a strong resource area would achieve. It sits below Lazard for nuclear, because Lazard anchors on the actual cost of Vogtle units 3 and 4, which came in at an estimated $169 and $228 per megawatt-hour after well-documented overruns, while this page uses the engineering estimate for a plant built to schedule. The gap between those two nuclear numbers, roughly $109 against $169 to $228, is the single most expensive lesson in recent US energy construction.